09/21/17 – Arlington ISD – Arlington HS, Morton ES & South Davis ES Renovations – Thursday, September 21, 2017 at 2:00 P.M.
Budget:  $ 17,465,247.00

09/27/17 – Public Transit Services – New Multi-Modal Transit Facility – Wednesday, September 27, 2017 at 2:00 P.M.
Budget:  $ 10,000,000.00

10/10/17 – Dallas ISD BP#018 – Sarah Zumwalt MS Renovations – Tuesday, October 10, 2017 at 2:00 P.M.
Budget:  $ 3,383,052.00

Scope:
Secure vestibule is planned for the entry of the school.  1 office will need to be renovated along with portion of the entry and main office.
All Corridors will have the VCT flooring replaced with new VCT, walls will be painted with a few murals to be preserved, metal lockers to be removed, and ceiling to be replaced with new acoustical ceiling tile, but existing lights and ceiling accessories are to remain.
General Classrooms will have the flooring replaced with new VCT, walls will be painted, replace acoustical ceiling tile/grid system, but existing lights and ceiling accessories are to remain.  The existing chalkboards will be covered with new white boards and the wood frames painted to match walls.  The existing cabinets will be removed and new district standard cabinets will be installed.
Science labs will replace the flooring with new VCT, walls will be painted, and ceiling will be replaced with new acoustical ceiling tiles/grid system, existing lights are to remain.  The existing chalkboards will be covered with new white boards and the wood frames painted to match walls.  The existing cabinets by the window will be removed and new district standard cabinets will be installed.  The other cabinets with existing epoxy countertops will remain and receive new cabinet doors and hardware, and refinish all exposed surfaces to match all cabinets.
Band room and adjacent practice rooms will replace the flooring with new VCT, walls will be painted, and ceiling will be replaced with new acoustical ceiling tiles/grid system.
Library will have the ceiling tile replaced with new acoustical ceiling tiles/grid system, existing lights to remain.  Walls will be painted and spot repairs to the floor.
Cafeteria will have the ceiling replaced with new acoustical ceiling tiles/grid system, existing lights are to remain.  Walls will be painted and spot repairs to the floor.
Gyms, boys’ and girls’, will have walls painted and replace side basketball goals and walls pads behind goals.
Art room will have all existing cabinets replaced with district standard cabinets for an art room.  Flooring and ceiling will be replaced and walls painted.
Computer labs will replace flooring and ceiling and walls will be painted.
Throughout the school, steam heating systems will be removed and a new hydronic heating system with duct heating coils will be installed.

Louisiana

**Please email Holly Guillot for password to download Plans/Specifications & Addenda or to be added to our Invitation to Bid list –holly.guillot@ratcliffconstruction.com

** To access plans/specifications & addenda – Please see call Holly Guillot at 318-448-0826 for password to gain access to ‘Project Downloads’ in the Subcontractor Portal

 

09/05/2017 – Lake Elementary School Flood Damage Restoration – Bids Tuesday, September 05, 2017 @ 2:00 P.M.

Budget:  $ 6,300,000

Project Scope:

1. To restore the damaged facilities to pre-flood conditions with alternates for APSB and Code Required Upgrades.

2. Maintain Temporary Campus operations, including vehicular traffic patterns, parking arrangements and pedestrian pathways.

3. Project includes installation of new gypsum board with veneer plastering at existing interior and exterior walls, new ceiling tiles, new finishes, new building insulation, new doors, frames and hardware, new millwork per ASPB standards, new HVAC equipment, new plumbing fixtures, new electrical improvements to service new equipment and restoration of existing electrical syst